Thursday 8 March 2018

PCI & HANDOVER!!!!

So I had the PCI on the 2nd March after it got pushed back a bit which was really frustrating. It went very well with only a few cosmetics issues like paint to fix up. The side of the house on the boundary needs to be rendered as it was poorly bricked from the inside out. The motar has squeezed out the side and they didn't bother to wipe it off. Other than that minor things which could be fixed.

I paid a private building inspector to come and do the inspection for me as I would not have a clue of what to look for. He was fantastic!

HANDOVER TOMORROW!!! WOOHOO Finally after 2 years and 8 months! It has been a loooooooong journey!

I get the keys at 1pm so I will be cleaning the house ready for the furniture to be delivered on Saturday. The couch won't be in until next Thursday but the rest will. So much to do still including sealing the grout and tiles which was a suggestion by a few of our friends to help with cleaning down the line. Then of course there is the landscaping which needs to be done in the courtyard, backyard and front.

Anyhow.. now for some picture updates!


Loving my aggregate driveway upgrade





More pics to come at Handover!!




Wednesday 24 January 2018

16 Week Update!

It has officially been 16 weeks and the builders are running a bit behind so they will now have to compensate me $330/week for every week they are delayed.

The painting and tapware has been done so the house is starting to all come together. The doors are in. Not much left to do! The shelving needs to be built for the walk ins/pantry. Downlights/lights and switches. Door stops, flooring, rendering outside and concrete.

Hoping to move in around the end of FEB! Now.. for the pictures!












Tuesday 16 January 2018

Furniture Shopping!

Over the break we got all the furniture for the house!


We chose these chairs, but in a lighter grey because the couch is already dark grey.







Tiling & Painting

The end of year rush took over so I didn't get a chance to update. There was not much done to the house after the plastering as the builders were on break for 3 week. The tiling has been done and they started the painting a few days ago. This should also be finished by now but I have not had a chance to drop in.

Loving my Bevel white Tiles in the kitchen and so glad I changed it to white grout so it does not look so "cafe like"









Thursday 7 December 2017

Plastering

Bricks have been cleaned and plastering done. The plastering went up really quick. Only took them about a day (benefits of a small property). I've been told the joinery (cabinets etc) is going in on the 13th December!








Wednesday 29 November 2017

Bricks

Haven't posted for a while as there was a bit of a delay with the bricks. The colour I had chosen (Austral Truffle) was out of stock and I had to choose a different one (Austral pepperwood). They started and then I realised that the motar was natural when I had paid to upgrade to off white. I had them continue to keep with the timeframe and get refunded. They were going to go over it with nawkaw but I was concerned that it might not look that good and I heard it can discolour the bricks.






Tuesday 17 October 2017

Roof

The roof is up and they have put the sheets on in preparation for the insulation and brick.

The brickwork will start at the end of this week or early next week. 


It was definitely worth it spending the extra $3000 for the extended ceiling height. The standard is 2.4m. My ceiling height is 2.7m I think this gives the house a bigger feel given its small in size. It's higher than both of my neighbours which is nice. The flat roof tiles were part of a free upgrade for me which I'm really happy about. Gives the house a more modern look.